A Model to Select Project Delay Analysis Method in Downstream Oil and Gas Industry: A Case Study

Authors

    Seyyed Abdollah Razavi * Department of Energy Economics and Management, Tehran Faculty of Petroleum, Petroleum University of Technology (PUT), Abadan, Iran
    Esmaeel Ordoei Department of Energy Economics and Management, Tehran Faculty of Petroleum, Petroleum University of Technology (PUT), Abadan, Iran

Keywords:

Project Management , Project Delay Analysis , Delay Analysis Methods (DAM), Oil and Gas Industry, Decision Support Model

Abstract

Projects are bound by contractual completion dates, and delays necessitate determining liability between parties. Given the varying outcomes of different delay analysis methodologies and the significant contractual implications, selecting an appropriate method is crucial. This study presents a model for selecting optimal delay analysis methods for engineering, procurement, construction, and installation projects in Iran's oil and gas industry. The model evaluates four common methodologies: "As-planned versus As-built," "Impacted As-Planned," "Collapsed As-Built," and "Windows Analysis," each suited to specific project characteristics. The research employs Fuzzy Delphi method for criteria validation and Analytic Hierarchy Process (AHP) for method selection across five project categories.

Downloads

Download data is not yet available.

References

Y. Abdelhadi, M. F. Dulaimi & A. Bajracharya, International Journal of Construction Management., 2019, 19(4), 329-340.

D. Arditi & T. Pattanakitchamroon, International Journal of Project Management., 2006, 24(2), 145-155.

N. Braimah & I. Ndekugri., International Journal of Project Management., 2008, 26(7), 789-799.

M. Cevikbas & Z. Işık, Engineering, Construction and Architectural Management., 2023, 30(6), 2463-2480.

B. L. Golden, Q. Wang, Applications & studies., 1990 ,68-81. Springer.

A. Himawan & A. Arviansyah, Sustainable future: Trends, strategies and development., 2023. Taylor & Francis.

C. Kabre & P. Kumar, Construction Engineering and Architecture., 2019, 19(4), 52-59.

N. H. Muhamad, M. F. Mohammad, A. Ahmad & I. H Ibrahim, Procedia-Social and Behavioral Sciences., 2016, 222, 121-131.

J. Yang, D. Arditi, D. Lee & I. Mutis, Journal of Civil Engineering., 2022, 26(12), 4926-4941.

C. Munvar, D. G. Mengistu, & G. Mahesh, Journal of Legal Affairs and Dispute Resolution in Engineering and Construction., 2019 12(1), 04519028.

H. Taherdoost, International Journal of Economics and Management Systems., 2017, 2, 243-246.

N. A. Jalaliyoon, Bakar & H. Taherdoost, International Journal of Academic Research in Management., 2012, 1(1), 1-9.

Graphical Abstract

Published

2025-04-01