A Model to Select Project Delay Analysis Method in Downstream Oil and Gas Industry: A Case Study

Authors

    Seyyed Abdollah Razavi * Petroleum University of Technology in Tehran, Iran
    Mohammad Ali Hatefi Petroleum University of Technology in Tehran, Iran
    Esmaeel Ordoei Petroleum University of Technology in Tehran, Iran

Keywords:

Project Management , Project Delay Analysis , Delay Analysis Methods (DAM), Oil and Gas Industry, Decision Support Model

Abstract

Projects are bound by contractual completion dates, and delays necessitate determining liability between parties. Given the varying outcomes of different delay analysis methodologies and the significant contractual implications, selecting an appropriate method is crucial. This study presents a model for selecting optimal delay analysis methods for engineering, procurement, construction, and installation projects in Iran's oil and gas industry. The model evaluates four common methodologies: "As-planned versus As-built," "Impacted As-Planned," "Collapsed As-Built," and "Windows Analysis," each suited to specific project characteristics. The research employs Fuzzy Delphi method for criteria validation and Analytic Hierarchy Process (AHP) for method selection across five project categories.

Downloads

Download data is not yet available.

Published

2025-04-01

Issue

Section

Articles

How to Cite

Seyyed Abdollah Razavi, Mohammad Ali Hatefi, & Esmaeel Ordoei. (2025). A Model to Select Project Delay Analysis Method in Downstream Oil and Gas Industry: A Case Study. Jeecpjournal, 2(2). https://jeecpjournal.com/index.php/jeecp/article/view/17